Grate Cooler ESP Inlet Wall Replacement, Co. Louth
Tusker Steelworks Limited
Finalist in: Architectural Metalwork - Special Projects
Project Gallery
The Story
Tusker was commissioned by Irish Cement to replace an ageing Electrostatic Precipitator (ESP) Inlet Wall filter system, essential for emissions control and environmental compliance. The project required a complete end-to-end solution, which Tusker delivered entirely in-house — covering design, fabrication, transport, and installation.
The existing ESP system had become inefficient and difficult to maintain. Tusker’s objective was to deliver a high-performance replacement that would improve particulate capture, integrate with existing infrastructure, reduce maintenance, and provide long-term durability. A bespoke modular system was developed to suit the site’s spatial constraints.
Key innovations included optimised airflow, improved electrode configuration, and a modular design for off-site fabrication and easier on-site assembly. Fabrication took place at Tusker’s facility, incorporating 150mm-thick specialist insulation rated to 650°C, and custom-rolled aluminium cladding for durability and thermal performance. Precision welding ensured all internal joints were airtight.
The structure was transported as abnormal loads, assembled on-site, and lifted into position using in-house designed and tested lifting beams — minimising crane time and installation risk. During the same shutdown window, Tusker also replaced drag chains, bearings, and serviced mechanical systems.
The completed system significantly improved efficiency, reliability, and compliance, and was delivered safely, on time, and within budget.
"This project exemplifies engineering excellence, innovation, and quality. Tusker’s ability to deliver a complex, high-performance system entirely in-house, from design to installation, demonstrates unmatched capability and coordination. The use of specialist materials, custom lifting solutions, and seamless execution make this a benchmark project in industrial engineering. Tusker recently achieved a significant milestone by successfully completing our full external recertification audits for both ISO 14001 (Environmental Management) and ISO 45001 (Occupational Health & Safety Management) standards, with zero non-conformities raised. In addition, Tusker holds the following certifications: EN 1090 Execution Class 4 – the highest level of certification for structural steel fabrication in Europe, demonstrating our capability to deliver complex and safety-critical structures. ISO 3834 – confirming our compliance with international standards for welding quality, ensuring the integrity and reliability of welded components in demanding applications. ISO 9001 – reflecting our dedication to consistent quality management and continuous improvement. These certifications collectively highlight Tusker’s commitment to excellence, compliance, and industry leadership."
— Tusker
Project Team
The project was delivered by a multidisciplinary in-house team at Tusker.
Share This Project
2025 Irish Steel Awards Winner
Congratulations to Tusker Steelworks Limited for winning an Irish Steel Award!
More in Architectural Metalwork - Special Projects
Other shortlisted projects in this category
Bike Shelter, Kilkenny
Graepel Perforators and Weavers Ltd
Let’s be clear — it’s a bike shelter, not a national scandal! Ours didn’t cost €336,000, to make, it didn’t need a review, and didn’t make the news. But may just win an award! Our bike shelter is just smart design, solid manufacturing, without drama. Other reasons... This project is a bespoke Picture-Perf design which showcases our capabilities and perforating techniques, transforming a functional piece into a contemporary work of urban art—a solid example of how metalwork can enhance public inf
Bridges, Cherrywood, Dublin
Graepel Perforators and Weavers Ltd
The Cherrywood Bridges project captures the essence of what the Irish Steel Awards aim to recognise: innovation, engineering excellence, environmental sensitivity, and collaborative craftsmanship. Graepels’ role extended beyond supply and manufacture—this was a creative partnership. Working with CME Industrial Specialists, MOLA Architects, and the broader Cherrywood team, we helped bring a biophilic design vision to life using precision-engineered Cor-Ten steel. Spanning between timber-clad pods
New Children's Hospital, Concourse Stairs Balustrades
OMC Technologies
This project is a showcase of what’s possible when design intent, fabrication precision, and installation excellence are brought into perfect alignment. The Leaf Pattern Balustrade is not just a visual architectural feature—it is the result of an exceptional collaborative effort between design managers, fabricators, and installers. From the outset, the design demanded an uncompromising commitment to detail. The leaf pattern manually laid out and unique across every panel, required a rare level o